Deck Shoring progressing at Level P1 Area 3
Rebar & MEP rough-in started at Level P1 Area 2
Concrete pour for Level P1 Area 2 scheduled for 10/12/21
Perimeter walls, columns & shear walls in progress at Level P1 Area 4
Waterproofing being installed up to grade at South elevation
CMU walls start installation at Garage Levels P4 & P5
top of page


WHERE PASSION, PURPOSE,
& PROGRESS
MEET
We invite you to follow West's construction progress...
Deck Shoring complete at Level P2-P1 ramp
Rebar & MEP rough in being installed at Level P2-P1 ramp
Concrete pour for Level P2 Area 4 scheduled for 9/29/21
Perimeter walls, columns & shear walls in progress at Level P2 Area 2
Waterproofing being installed up to grade at East elevation
Deck Shoring complete at Level P2
Rebar & MEP rough in being installed at Level P2 Area 3
Concrete pour for Level P2 Area 2 scheduled for 9/22/21
Perimeter walls, columns and shear walls in progress at Level P2 Area 1
Waterproofing being installed up to grade at Southeast elevation