We invite you to follow West's construction progress...
  • Unit drywall in progress at Level 35 & 36

  • Unit paint in progress at Level 34

  • Unit cabinets in progress at Level 33

  • Unit Bath/Shower surround tile in progress at Level 34

  • Unit countertops in progress at Level 33

  • Unit LVP flooring in progress at Level 30

  • Unit appliances in progress at Level 28

  • Punch list in progress at Level 17

  • Site concrete and paving in progress at Level 1

  • Flooring tile finishes starting at Level 9 Amenities

  • MEP rough-in in progress at Level 37 Amenities




  • Unit drywall in progress at Level 35

  • Unit paint in progress at Level 34

  • Unit cabinets in progress at Level 33

  • Unit Bath/Shower surround tile in progress at Level 34

  • Unit countertops in progress at Level 32

  • Unit LVP flooring in progress at Level 30

  • Unite appliances in progress at Level 27

  • Punch list in progress at Level 17

  • Wood finishes in progress at Level 9 Amenities

  • MEP rough-in in progress at Level 37 Amenities




  • Metal framing in progress at Level 37

  • Unit Tape & Finish in progress at Level 34

  • Unit Paint in progress at Level 34

  • Unit Cabinets in progress at Level 33

  • Unit Bath/Shower Surround Tile in progress at Level 34

  • Unit Countertops in progress at Level 31

  • Unit LVP Flooring in progress at Level 29

  • Unit Appliances in progress at Level 27

  • Punch list in progress at Level 17

  • Wood finishes in progress at Level 9 Amenities

  • MEP Rough-in in progress at Level 37 Amenities