April 10 - 14, 2023

  • Deck shoring complete at Level 36

  • Deck concrete placement at Level 36 scheduled for 4/20/23

  • MEPF rough-in in progress through Level 35

  • Window Wall in progress at Level 29

  • Metal framing in progress at Level 26

  • Unit production drywall in progress at Level 16

  • Unit tape and finish in progress at Level 15

  • Unit paint in progress at Level 14

  • Unit cabinets and bath surround tile in progress at Level 11

  • Unit countertops in progress at Level 10