Deck shoring complete at Level 36
Deck concrete placement at Level 36 scheduled for 4/20/23
MEPF rough-in in progress through Level 35
Window Wall in progress at Level 29
Metal framing in progress at Level 26
Unit production drywall in progress at Level 16
Unit tape and finish in progress at Level 15
Unit paint in progress at Level 14
Unit cabinets and bath surround tile in progress at Level 11
Unit countertops in progress at Level 10