Deck Shoring in progress at Level 6 Area 3
Rebar and MEP rough-in progressing at Level 6 Area 3
Deck concrete placement at Level 6 Area 3 scheduled for 4/21/22
Rebar column cages and formwork in progress at Level 6 Area 2
MEPF equipment install in progress at Garage Level P5-Level 1