top of page

April 11-15, 2022

  • Deck Shoring in progress at Level 6 Area 3

  • Rebar and MEP rough-in progressing at Level 6 Area 3

  • Deck concrete placement at Level 6 Area 3 scheduled for 4/21/22

  • Rebar column cages and formwork in progress at Level 6 Area 2

  • MEPF equipment install in progress at Garage Level P5-Level 1


bottom of page