April 17 - 21, 2023

  • Deck shoring complete at Level 36

  • Deck concrete placement at Level 36 scheduled for 4/25/23

  • MEPF rough-in in progress through Level 36

  • Window Wall in progress at Level 29

  • Metal framing in progress at Level 27

  • Unit production drywall in progress at Level 17

  • Unit tape and finish in progress at Level 16

  • Unit paint in progress at Level 14

  • Unit cabinets and bath surround tile in progress at Level 11

  • Unit countertops in progress at Level 10