April 24 - 28, 2023

  • Deck shoring complete at Level 37

  • Deck concrete placement at Level 36 scheduled for 5/11/23

  • MEPF rough-in in progress through Level 36

  • Window Wall in progress at Level 30

  • Metal framing in progress at Level 28

  • Unit production drywall in progress at Level 18

  • Unit tape and finish in progress at Level 17

  • Unit paint in progress at Level 16

  • Unit cabinets and bath surround tile in progress at Level 12

  • Unit countertops in progress at Level 10