Deck Shoring in progress at Level 6 Area 3
Rebar and MEP rough-in progressing at Level 6 Area 2
Deck concrete placement at Level 6 Area 2 scheduled for 4/13/22
Rebar column cages and formwork in progress at Level 6 Area 1
MEPF equipment install in progress at Garage Level P5-Level 1
top of page
bottom of page