August 1-5, 2022

  • Deck shoring complete at Level 12

  • Rebar and MEP rough-in complete at Level 12

  • Deck concrete placement at Level 12 to occur on 8/9/22

  • MEPF rough-in continues throughout Level P5 - Level 9

  • Exterior glazing in progress at Level 4 along Front Street

  • Metal framing in progress at Garage Levels P5-L3