Deck shoring complete at Level 12
Rebar and MEP rough-in complete at Level 12
Deck concrete placement at Level 12 to occur on 8/9/22
MEPF rough-in continues throughout Level P5 - Level 9
Exterior glazing in progress at Level 4 along Front Street
Metal framing in progress at Garage Levels P5-L3