Deck shoring in progress at Level 14
Deck concrete placement at Level 14 to occur on 8/25/22
MEPF rough-in continues throughout Level P5 - Level 12
Exterior glazing in progress at Level 2 along Union
Metal framing in progress at Garage Levels P5-L5