Window Wall in progress at Level 36
Metal framing in progress at Level 35
Unit tape and finish in progress at Level 30
Unit paint in progress at Level 27
Unit cabinets in progress at Level 24
Unit Bath/Shower surround tile in progress at Level 25
Unit countertops in progress at Level 21
Unit LVP flooring in progress at Level 19
Rough clean in progress at Levell 11 Residential Units
Tree planting in production at Level 9 Amenity Deck
Pool deck installation in progress at Level 37