August 29-September 2, 2022

  • Deck shoring complete at Level 15

  • Deck concrete placement at Level 15 to occur on 9/2/22

  • MEPF rough-in continues throughout Level P5 - Level 15

  • Exterior glazing in progress at Level 8

  • Metal framing in progress at Garage Level P5-Level 7