August 7 - 11, 2023

  • Window Wall in progress at Level 35

  • Metal framing in progress at Level 34

  • Unit tape and finish in progress at Level 33

  • Unit paint in progress at Level 26

  • Unit cabinets in progress at Level 21

  • Unit Bath/Shower surround tile in progress at Level 22

  • Unit countertops in progress at Level 19

  • Unit LVP flooring in progress at Level 16

  • Lightweight soil being pumped at Level 9 Amenity Deck

  • Pool equipment room framing began this week