Deck shoring, rebar and in-slab MEP in progress at Level 13
Deck concrete placement at Level 13 to occur on 8/17/22
MEPF rough-in continues throughout Level P5 - Level 11
Exterior glazing in progress at Level 5 along Front Street
Metal framing in progress at Garage Levels P5-L4