top of page

December 11 - 15, 2023

  • Window Wall in progress at Level 37

  • Metal framing in progress at Level 37

  • Unit tape and finish in progress at Level 34

  • Unit paint in progress at Level 34

  • Unit cabinets in progress at Level 33

  • Unit Bath/Shower surround tile in progress at Level 34

  • Unit countertops in progress at Level 31

  • Unit LVP flooring in progress at Level 28

  • Unite appliances in progress at Level 26

  • Punch list in progress at Level 16

  • Wood finishes in progress at Level 9 Amenities

  • Frame ceilings in progress at Level 37 Amenities




bottom of page