Deck shoring in progress at Level 27
Deck concrete placement at Level 27 to occur on 1/6/23
MEPF rough-in in progress through Level 26
Window Wall in progress at Level 19
Metal framing in progress at Level 17
Drywall pre-hang in progress at residential units Level 13
Interior wall insulation in progress at Level 10
Unit drywall in progress at Level 9