February 12 - 16, 2024

  • Drywall and MEP rough-in complete at Level 37 Interior Amenities

  • Glass guardrail ongoing at Level 37 Exterior Amenities

  • Interior Gym restroom finishes in progress at Level 9

  • Wall stone in progress at Level 1 lobby

  • Taping in progress at Penthouse units Level 35 & 36

  • Residential unit Penthouse cabinets underway

  • Residential unit countertops in progress at Level 34

  • Residential unit LVP Flooring in progress at Level 33

  • Residential unit Appliances in progress at Level 32

  • Punch list in progress at residential units Level 21

  • Office restroom finishes in progress

  • Elevator lobby finishes in progress up to Level 28