  • Deck shoring complete at Level 32

  • Deck concrete placement at Level 32 occurring on 2/23/23

  • MEPF rough-in in progress through Level 32

  • Window Wall in progress at Level 24

  • Metal framing in progress at Level 21

  • Interior wall insulation in progress at Level 12

  • Unit production drywall in progress at Level 10

  • Unit tape and finish in progress at Level 9