February 19 - 23, 2024

  • Fire feature installation ongoing at Level 37 Interior Amenities

  • Waterproofing for paver installation at Level 37 Exterior Amenities

  • Glass guardrail ongoing and near completion at Level 37 Exterior Amenities

  • Interior Gym restroom finishes in progress at Level 9

  • Wall stone in progress at Level 1 lobby

  • Drywall in progress at Level 1 lobby

  • Preparation for flooring installation in progress at Level 1

  • Perforated metal panel and ACM Panels at storefront installed at Level 1 Exterior

  • Street trees installation in progress at Level 1 Exterior Amenity

  • Paver installation in progress at Level 1 Exterior

  • Parking Garage striping in progress

  • Parking Garage storage lockers completely installed

  • Punch list in progress at residential units Level 22

  • Office restroom finishes in progress