February 6 - 10, 2023

  • Deck shoring complete at Level 31

  • Deck concrete placement at Level 31 occurring on 2/14/23

  • MEPF rough-in in progress through Level 31

  • Window Wall in progress at Level 23

  • Metal framing in progress at Level 20

  • Interior wall insulation in progress at Level 12

  • Unit production drywall in progress at Level 10

  • Unit tape and finish in progress at Level 9