Deck shoring in progress at Level 29
Deck concrete placement at Level 29 to occur on 1/27/23
MEPF rough-in in progress through Level 28
Window Wall in progress at Level 21
Metal framing in progress at Level 17
Interior wall insulation in progress at Level 12
Unit production drywall in progress at Level 10
Unit tape and finish in progress at Level 9