Deck shoring in progress at Level 27
Deck concrete placement at Level 27 to occur on 1/9/23
MEPF rough-in in progress through Level 27
Window Wall in progress at Level 20
Metal framing in progress at Level 17
Interior wall insulation in progress at Level 11
Unit drywall in progress at Level 10
Unit tape and finish in progress at Level 9