January 22 - 26, 2024

  • Interior Amenities drywall and MEP rough-in ongoing at Level 37

  • Interior Amenities tile at restrooms in progress at Level 9

  • Interior Amenities framing walls and ceilings in progress at Level 1

  • Penthouse unites Level 35 & 36 in progress

  • Residential unit cabinets in progress at Level 34

  • Residential unit countertops in progress at Level 33

  • Residential unit LVP Flooring in progress at Level 30

  • Residential unit Appliances in progress at Level 28

  • Punch list in progress at residential units Level 19

  • Site concrete and Union Street planters in progress at Level 1

  • Exterior Amenities glass guardrail install in progress at Level 37