January 23 - 27, 2023

  • Deck shoring complete at Level 29

  • Deck concrete placement at Level 29 occuring on 1/27/23

  • MEPF rough-in in progress through Level 29

  • Window Wall in progress at Level 21

  • Metal framing in progress at Level 18

  • Interior wall insulation in progress at Level 12

  • Unit production drywall in progress at Level 10

  • Unit tape and finish in progress at Level 9