January 30 - February 3, 2023

  • Deck shoring complete at Level 30

  • Deck concrete placement at Level 30 occurring on 2/6/23

  • MEPF rough-in in progress through Level 30

  • Window Wall in progress at Level 22

  • Metal framing in progress at Level 19

  • Interior wall insulation in progress at Level 12

  • Unit production drywall in progress at Level 10

  • Unit tape and finish in progress at Level 9