January 9 - 13, 2023

  • Deck shoring in progress at Level 28

  • Deck concrete placement at Level 27 to occur on 1/19/23

  • MEPF rough-in in progress through Level 28

  • Window Wall in progress at Level 21

  • Metal framing in progress at Level 16

  • Interior wall insulation in progress at Level 12

  • Unit drywall in progress at Level 10

  • Unit tape and finish in progress at Level 9