Deck shoring in progress at Level 28
Deck concrete placement at Level 27 to occur on 1/19/23
MEPF rough-in in progress through Level 28
Window Wall in progress at Level 21
Metal framing in progress at Level 16
Interior wall insulation in progress at Level 12
Unit drywall in progress at Level 10
Unit tape and finish in progress at Level 9
top of page
bottom of page