Window Wall in progress at Level 34
Metal framing in progress at Level 33
Unit tape and finish in progress at Level 30
Unit paint in progress at Level 21
Unit cabinets in progress at Level 18
Unit Bath/Shower surround tile in progress at Level 21
Unit countertops in progress at Level 16
Unit LVP flooring in progress at Level 13
Amenity Deck waterproofing and planter walls in production at Level 9
Pool and spa delivered and hoisted to Level 37