Deck shoring complete at Level 10
Rebar and MEP rough-in complete at Level 10
Deck concrete placement at Level 10 to occur on 7/22/22
Rebar column cages and formwork in progress at Level 10
MEPF rough-in continues throughout Level P5 - Level 8
Exterior glazing in progress at Level 3 along Front Street
Metal framing in progress at Garage Levels P5-P1