July 25-29, 2022

  • Deck shoring complete at Level 11

  • Rebar and MEP rough-in complete at Level 11

  • Deck concrete placement at Level 11 to occur on 8/1/22

  • Rebar column cages and formwork in progress at Level 10

  • MEPF rough-in continues throughout Level P5 - Level 9

  • Exterior glazing in progress at Level 4 along Front Street

  • Metal framing in progress at Garage Levels P5-P2