Deck shoring complete at Level 11
Rebar and MEP rough-in complete at Level 11
Deck concrete placement at Level 11 to occur on 8/1/22
Rebar column cages and formwork in progress at Level 10
MEPF rough-in continues throughout Level P5 - Level 9
Exterior glazing in progress at Level 4 along Front Street
Metal framing in progress at Garage Levels P5-P2