Window Wall in progress at Level 34
Metal framing in progress at Level 31
Unit tape and finish in progress at Level 27
Unit paint in progress at Level 20
Unit cabinets in progress at Level 16
Unit Bath/Shower surround tile in progress at Level 20
Unit countertops in progress at Level 15
Unit LVP flooring in progress at Level 12
Amenity Deck waterproofing and planter walls in production at Level 9
Pool delivery tracking for 7/10/23