July 31 - August 4, 2023

  • Window Wall in progress at Level 35

  • Metal framing in progress at Level 34

  • Unit tape and finish in progress at Level 32

  • Unit paint in progress at Level 26

  • Unit cabinets in progress at Level 20

  • Unit Bath/Shower surround tile in progress at Level 22

  • Unit countertops in progress at Level 19

  • Unit LVP flooring in progress at Level 15

  • Approaching landscaping installation at Level 9 Amenity Deck

  • Pool and spa welding of stainless steel inner connection completed