June 19 - 23, 2023

  • Concrete placement at Tower roof complete

  • Window Wall in progress at Level 33

  • Metal framing in progress at Level 31

  • Unit tape and finish in progress at Level 22

  • Unit paint in progress at Level 20

  • Unit cabinets in progress at Level 16

  • Unit Bath/Shower surround tile in progress at Level 19

  • Unit countertops in progress at Level 14

  • Unit LVP flooring in progress at Level 11

  • Amenity Deck waterproofing and planter walls in production at Level 9

  • Amenity Deck pool waterproofing in production at Level 37