June 20-24, 2022

  • Deck shoring complete at Level 9 Area 3

  • Rebar and MEP rough-in in progress at Level 9 Area 2

  • Deck concrete placement at Level 9 Area 1 to occur on 6/27/22

  • Rebar column cages and formwork in progress at Level 9 Area 1

  • MEPF rough-in continues throughout Level P5 - Level 4

  • Exterior glazing started at Level 1 along Front Street

  • Layout and framing started at Garage Level P5