Deck shoring complete at Level 9 Area 3
Rebar and MEP rough-in in progress at Level 9 Area 2
Deck concrete placement at Level 9 Area 1 to occur on 6/27/22
Rebar column cages and formwork in progress at Level 9 Area 1
MEPF rough-in continues throughout Level P5 - Level 4
Exterior glazing started at Level 1 along Front Street
Layout and framing started at Garage Level P5