June 27-July 1, 2022

  • Deck shoring complete at Level 9 Area 3

  • Rebar and MEP rough-in in progress at Level 9 Area 3

  • Deck concrete placement at Level 9 Area 3 to occur on 7/14/22

  • Rebar column cages and formwork in progress at Level 9 Area 2

  • MEPF rough-in continues throughout Level P5 - Level 5

  • Exterior glazing started at Level 1 along Front Street

  • Metal framing in progress at Garage Levels P5-P2