Concrete formwork Roof Core Walls in progress up to Level 40
Window Wall in progress at Level 32
Metal framing in progress at Level 31
Unit production drywall in progress at Level 22
Unit tape and finish in progress at Level 21
Unit paint in progress at Level 19
Unit cabinets in progress at Level 14
Unit Bath/Shower surround tile in progress at Level 17
Unit countertops in progress at Level 13
Unit LVP flooring in progress at Level 10