top of page

June 5 - 9, 2023

  • Concrete formwork Roof Core Walls in progress up to Level 40

  • Window Wall in progress at Level 32

  • Metal framing in progress at Level 31

  • Unit production drywall in progress at Level 22

  • Unit tape and finish in progress at Level 21

  • Unit paint in progress at Level 19

  • Unit cabinets in progress at Level 14

  • Unit Bath/Shower surround tile in progress at Level 17

  • Unit countertops in progress at Level 13

  • Unit LVP flooring in progress at Level 10



bottom of page