June 6-10, 2022

  • Deck shoring complete at Level 9 Area 2

  • Rebar and MEP rough-in in progress at Level 9 Area 1

  • Deck concrete placement at Level 9 Area 1 to occur on 6/20/22

  • Rebar column cages and formwork in progress at Level 8 Area 3

  • MEPF rough-in continues throughout Level P5 - Level 3

  • Backfill to grade complete at Level 1 along Front Street