Deck shoring complete at Level 9 Area 2
Rebar and MEP rough-in in progress at Level 9 Area 1
Deck concrete placement at Level 9 Area 1 to occur on 6/20/22
Rebar column cages and formwork in progress at Level 8 Area 3
MEPF rough-in continues throughout Level P5 - Level 3
Backfill to grade complete at Level 1 along Front Street