March 14-18, 2022

  • Deck Shoring in progress at Level 5 Area 3

  • Rebar and MEP rough-in progressing at Level 5 Area 2

  • Deck concrete placement at Level 5 Area 2 scheduled for 3/21/22

  • Rebar column cages and formwork in progress at Level 5 Area 1

  • Mechanical and fire equipment installation in progress throughout Garage Levels