March 20 - 24, 2023

  • Deck shoring complete at Level 34

  • Deck concrete placement at Level 34 scheduled for 3/28/23

  • MEPF rough-in in progress through Level 34

  • Window Wall in progress at Level 27

  • Metal framing in progress at Level 24

  • Unit production drywall in progress at Level 14

  • Unit tape and finish in progress at Level 13

  • Unit paint in progress at Level 11

  • Unit cabinets and bath surround tile in progress at Level 10

  • Unit countertops in progress at Level 9