Deck Shoring in progress at Level 6 Area 1
Rebar and MEP rough-in progressing at Level 5 Area 3
Deck concrete placement at Level 5 Area 3 scheduled for 3/29/22
Rebar column cages and formwork in progress at Level 5 Area 2
MEPF equipment install in progress at Garage Level P1-P5