March 21-25, 2022

  • Deck Shoring in progress at Level 6 Area 1

  • Rebar and MEP rough-in progressing at Level 5 Area 3

  • Deck concrete placement at Level 5 Area 3 scheduled for 3/29/22

  • Rebar column cages and formwork in progress at Level 5 Area 2

  • MEPF equipment install in progress at Garage Level P1-P5