March 27 - 31, 2023

  • Deck shoring complete at Level 35

  • Deck concrete placement at Level 35 scheduled for 4/6/23

  • MEPF rough-in in progress through Level 35

  • Window Wall in progress at Level 27

  • Metal framing in progress at Level 25

  • Unit production drywall in progress at Level 15

  • Unit tape and finish in progress at Level 14

  • Unit paint in progress at Level 11

  • Unit cabinets and bath surround tile in progress at Level 10

  • Unit countertops in progress at Level 9