Deck Shoring in progress at Level 6 Area 2
Rebar and MEP rough-in progressing at Level 6 Area 1
Deck concrete placement at Level 6 Area 1 scheduled for 4/6/22
Rebar column cages and formwork in progress at Level 5 Area 3
MEPF equipment install in progress at Garage Level P1-P5