March 4 - 8, 2024

  • Trellis paint in progress at Level 37 Exterior Amenities

  • Battens installed at pool showers at Level 37 Exterior Amenity

  • Shared kitchen ceiling millwork installed at Level 9 Interior Amenity

  • Stone floor install in progress at Level 1 Lobby

  • Wall tile in progress at Level 1 Leasing Office

  • Street trees Installation in progress at Level 1 Exterior Amenity

  • Paver installation in progress at Level 1 Exterior

  • Striping in progress at Parking Garage

  • Millwork in progress at P1 Mailroom

  • Punch list in progress at residential units 23 & 24

  • Office restroom finishes in progress