Deck Shoring in progress at Level 5 Area 3
Rebar and MEP rough-in progressing at Level 5 Area 1
Deck concrete placement at Level 5 Area 1 scheduled for 3/14/22
Rebar column cages and formwork in progress at Level 4 Area 3
Mechanical and fire equipment installation in progress throughout Garage Levels