Deck shoring complete at Level 37
Deck concrete placement at Level 36 scheduled for 5/11/23
MEPF rough-in in progress through Level 37
Window Wall in progress at Level 31
Metal framing in progress at Level 28
Unit production drywall in progress at Level 19
Unit tape and finish in progress at Level 18
Unit paint in progress at Level 16
Unit cabinets and bath surround tile in progress at Level 13
Unit countertops in progress at Level 11