May 13 - 17, 2024

  • Penthouse unit entry wall coverings are in progress at Level 35

  • Wood bench seating is being constructed in the L1 Lobby area  

  • Placement of Level 9 Fitness equipment has begun

  • Installation of projection screen in the Level 9 West Commons’ amenity space is ongoing

  • Emergency egress signage installed throughout the building

  • Testing and inspections ongoing for TCO

  • Residential unit owner punch list in progress thru Level 29