May 2-6, 2022

  • Deck Shoring in progress at Level 7 Area 3

  • Rebar and MEP rough-in complete at Level 7 Area 2

  • Deck concrete placement at Level 7 Area 1 occurring on 5/6/22

  • Rebar column cages and formwork in progress at Level 7 Area 1

  • MEPF rough-in continues throughout Garage Level P5-Level 2