Deck concrete placement at Roof Level 38 complete
MEPF rough-in in progress through Level 37
Window Wall in progress at Level 32
Metal framing in progress at Level 31
Unit production drywall in progress at Level 20
Unit tape and finish in progress at Level 19
Unit paint in progress at Level 17
Unit cabinets in progress at Level 13
Unit Bath/Shower surround tile in progress at Level 16
Unit countertops in progress at Level 12
Unit LVP flooring in progress at Level 10