May 22 - 26, 2023

  • Deck concrete placement at Roof Level 38 complete

  • MEPF rough-in in progress through Level 37

  • Window Wall in progress at Level 32

  • Metal framing in progress at Level 31

  • Unit production drywall in progress at Level 20

  • Unit tape and finish in progress at Level 19

  • Unit paint in progress at Level 17

  • Unit cabinets in progress at Level 13

  • Unit Bath/Shower surround tile in progress at Level 16

  • Unit countertops in progress at Level 12

  • Unit LVP flooring in progress at Level 10