May 23-27, 2022

  • Deck Shoring in progress at Level 8 Area 3

  • Rebar and MEP rough-in in progress at Level 8 Area 2

  • Deck concrete placement at Level 8 Area 2 occurring on 6/1/22

  • Rebar column cages and formwork in progress at Level 8 Area 1

  • MEPF rough-in continues throughout Garage Level P5-Level 3


.