Deck shoring complete at Level 8 Area 3
Rebar and MEP rough-in in progress at Level 8 Area 3
Deck concrete placement at Level 8 Area 3 to occur on 6/8/22
Rebar column cages and formwork in progress at Level 8 Area 1
MEPF rough-in continues throughout Level P5 - Level 3
Backfill to grade in progress at Level 1 along Front Street