May 6 - 10, 2024

  • Pool fill was completed at Level 37

  • Countertops & backsplashes substantially complete in all Amenity areas

  • Penthouse appliances are going in on Levels 35-36

  • Wall stone at the Level 1 Lobby stairs ongoing

  • EV charging stations and parking control access gate installed in garage

  • Evening commissioning and life safety testing ongoing

  • Residential unit owner punch list in progress through Level 29