May 8 - 12, 2023

  • Deck shoring complete at Level 37

  • Deck concrete placement at Level 37 north deck scheduled for 5/15/23

  • MEPF rough-in in progress through Level 37

  • Window Wall in progress at Level 31

  • Metal framing in progress at Level 29

  • Unit production drywall in progress at Level 19

  • Unit tape and finish in progress at Level 18

  • Unit paint in progress at Level 16

  • Unit cabinets in progress at Level 13

  • Unit Bath/Shower surround tile in progress at Level 14

  • Unit countertops in progress at Level 12

  • Unit LVP flooring in progress at Level 9