Deck shoring complete at Level 37
Deck concrete placement at Level 37 north deck scheduled for 5/15/23
MEPF rough-in in progress through Level 37
Window Wall in progress at Level 31
Metal framing in progress at Level 29
Unit production drywall in progress at Level 19
Unit tape and finish in progress at Level 18
Unit paint in progress at Level 16
Unit cabinets in progress at Level 13
Unit Bath/Shower surround tile in progress at Level 14
Unit countertops in progress at Level 12
Unit LVP flooring in progress at Level 9